Item number 819101-10 was changed to 819101-20 within 123456-100’s bill of material, which advanced the revision from C to D.
The effectivity for changing from the -10 item to the -20 item was 5/15/08.
As of today (8/20/08), it is discovered that the -20 items have severe deficiencies and will cause extensive problems if not replaced.
PLAN OF ACTION:
Replace the 819101-20’s with 819101-30’s.
Ship no more 987654-200’s with the -20 items.
Find all 987654-200s (including any shipped) and replace the 20s with -30s.
New -30 items can be available 2 weeks after vendor receipt of the Purchase Order (which will be generated upon release of the ECN today).
Map the receipts and issues of item number 819101-20 and account for the total quantity. How many have been ordered? Received? In inventory now? Incorporated into next higher assemblies?
How many 987654-200s have shipped containing the 819101-20s and what are their serial numbers?
What item numbers will you revise in the bill of material structure in order to replace 819101-20s with -30s? What will the effectivity be?
What additional information, if any, is needed to answer Question 2?
[meteor_slideshow slideshow=”arp2″]
A-Research-Paper.com is committed to deliver a custom paper/essay which is 100% original and deliver it within the deadline. Place your custom order with us and experience the different; You are guaranteed; value for your money and a premium paper which meets your expectations, 24/7 customer support and communication with your writer. Order Now
Use the order calculator below and get started! Contact our live support team for any assistance or inquiry.
[order_calculator]