operations-management Essay A manager must decide between two machin

A manager must decide between two machines. The manager will take into account each machine?s operating costs and initial costs, and its breakdown and repair times. Machine A has a projected average operating time of 140 hours and a projected average repair time of 14 hours. Projected times for machine B are an average operating time of 51 hours and a repair time of 7 hours. What are the projected availabilities of each machine?