A new-venture electronics firm is setting up its production facilities in Mexico. Product design is complete. The plant manager has hired 30 people, who possess mostly interchangeable skills, to prepare the plant. He has asked you to help him with resources allocation. He is unsure if he can meet the 30-week deadline, given his resource constraint. Schedule and resource information are shown below:a. Prepare an early-start schedule graph or Gantt chart and produce a histogram to show the resource loads. (please use excel)b. Create a revised schedule graph or Gantt chart, with accompanying histogram, to address the resource constraint of 30 people. (please use excel)c. Provide a short explanation for the plant manager about how you derived your revised schedule and what you recommend.