operations-management Essay All of the following convetions are wide

All of the following convetions are widely adopted project teams create the second level of the project Work Breakdown Structure (WBS) EXCEPT:A. The second level may be organized by project phase.B. The second level may be organized by major desing components.C.The second level may be organized by work funtion.D. The second level may be organized by activities and task.