Utilizing the Step-by-Step MRP Calculation Process, students will solve the following MRP problem given: Product A is an end item and is made from two units of B and four of C. B is made of three units of D and two of E. Product C is made of two units of F and two of E. Product A has a lead-time of one week. Products B, C and E have lead-times of two weeks. Products D and F have a lead-time of three weeks.

a. Show the bill of material (product structure tree).
b. If 100 units of A are required in week 10, develop the MRP planning schedule, specifying when items are to be ordered and received. There are currently no units of inventory on hand.

Grading Criteria:
Student will demonstrate their relevant knowledge of MRP
Apply critical thinking in applying MRP concepts
Create an Master Production Schedule and a Material Requirement Planning Chart
If there is a positive net requirement in a week, backward schedule by the lead-time and enter the quantity for the planned order release that will satisfy the net requirement.

[meteor_slideshow slideshow=”arp2″]

A-Research-Paper.com is committed to deliver a custom paper/essay which is 100% original and deliver it within the deadline. Place your custom order with us and experience the different; You are guaranteed; value for your money and a premium paper which meets your expectations, 24/7 customer support and communication with your writer. Order Now

Use the order calculator below and get started! Contact our live support team for any assistance or inquiry.